Status of items announced in the budget 2010-11 by Hon��ble MR


  1. Items Announced in Budget 10-11
  2. Gauge Conversion in NGP Divn.
  3. Targeted works 2010-11.
 

ON GOING PROJECTS


DOUBLING 

  • Item No. 116 ( XXIX) of Budget Speech
  • Durg Rajnandgaon 3rd line ( 30.889 Km)

   STATUS

  • Cost of project - `147.06 Crores.
  • Budget Grant -  `10.00 Crores. for 2010-11
  • Detailed estimate sanctioned in Oct. 10.
 

Items Announced in Budget 10-11 

Contd��


New Gauge Conversion works 

  • Item No 115 (i) Budget speech
  • Chhindwara -Nainpur Mandla Fort (182.25 Km)

    STATUS

  • Cost of project -  ` 556.54 Crores.
  • Budget Grant for 10 - 11: ` 1.00 Crores.
  • Detailed  part estimate  of  NIR - MFR for ` 145.8 Cr. Prepared.
 
 

Contd��


Completed Gauge Conversion Project  

  • Item No 113 (x) of Budget speech
    • Gondia - Balaghat including MOIL siding (42+7 Km) section commissioned in year 2005
    • Balaghat - Katangi [46.8] - Section completed & commissioned on 7.05.2010
 

Contd��


New line Project 

  • Item No 111 of Budget speech
  • Mandir Hasaud - Naya Raipur (20.00 Km) sanctioned as material modification to Raipur – Titlagarh doubling of East Coast Railway
  • Cost of project - ` 77.32 Crores.
  • Budget Grant for 2010-11 – Nil
  • Part estimate for ` 28 Lakhs. for preliminary activities sanctioned by  GM/SECR.
 

Contd��


Updating of Socially Desirable Rail Connectivity Proposals 

  • Item No 102 of Budget speech (Sr. No.10)
  • Barwadih- Chirimiri / Ambikapur [182km]
  • RET Survey report submitted on 17.05.03 for ` 406.86 Crs. with ROR (-) 4.85%. Updating done on 16.2.09. with ROR (-) 9.05%. Board again desired for updating. Updated estimate under finance vetting..
 

Contd��


                                               Updating of proposals  
Lohardaga-Korba (326 Km.)               (via Dharmjaygarh & Pathalgaon) 

  • Item No 102 of Budget speech (Sl No. 63)
  • Report Submitted to Rly. Board  in 2003.
  • Cost ` 621.67 crores & ROR (+) 07.25 %.
  • Updated estimate under calculation of ROR.
 

Contd��


 
                                                 
Updating of proposals  
Pendra Road Korba/Gevra Rd. (121.7 Km.) 
(via Pasan, Sundargarh & Deepika) 

  • Item No 102 of Budget speech (Sl. No. 82)
  • PET survey sanctioned in 1996-97.
  • Report submitted to Board in 2003.
  • Cost ` 344.43 Crores & ROR (+)15.23%.
  • Updated estimate under finance vetting.
 

Contd��


 
                                          Updating of proposals  
Raigarh - Mand Colliery to Bhupdeopur  
(63 Km. with Fly over) 

  • Item No 102 of Budget speech (Sl. No. 88)
  • PET survey sanctioned in 2008-09.
  • Report submitted to Railway Board in July -2009 at the cost of ` 310.64 Crores & ROR (+) 29.58%
  • Updated report submitted to Board in Aug. -10 at the cost of ` 344.20 crores and ROR (+) 26.33%
 

Contd��


                                                    Updating of proposals                       
Raipur Jharsuguda (310 Km.) 
(via. Kharotapalan, Baloda Bazar, Bhatgaon & Sarangarh.) 

  • Item No 102 of Budget speech (Sl. No. 89)
  • RET survey sanctioned in 1999-2000
  • Report submitted to Railway Board in Feb-2003.
  • Cost ` 971.96 crores & ROR (-) 20%.
  • Updating of abstract estimate is being done.
 

Contd��


                                                       Updating of proposals  
Ramtek Gotegaon (275 Km.) 
(via Khawasa, Sioni & Dhuma) 

  • Item No 102 of Budget speech (Sl. No. 92)
  • RET survey sanctioned in 1995.
  • Report submitted to Railway Board in April 1999.
  • Cost `. 528.21 crores & ROR (-) 11.50%
  • Updating in progress.
 

Contd��


                                                  Updating of proposals  
 

  • Item No 118 (i) of Budget speech
  • Wadsa -  Desaiganj - Gadchiroli - 49.5 Km (Cost sharing)
  • RET survey sanctioned in Aug -1995.
  • Initial report submitted in July - 1998.
  • Updated report submitted in Aug - 2010.
  • Cost ` 232.40 crores & ROR without sharing         (-) 3.88% & with 50% cost sharing by State Govt. ROR (-) 0.40%

 


Gauge conversion  
in  
NGP division


Section 

Blocking  

Opening  

(a) JBP - Sukrimangla (43.41km) 

Oct-2011 

June-2012 

(b) Sukrimangla-Nainpur (70.1 km)* 

Oct-2012 

June-2013 

* Subject to acquisition of forest land in Seoni Distt.  

(c) Nainpur – Mandla Fort (42.2 Km.)  

Oct -2012 

June -2013 

Planning of N.G. conversion in NGP Divn.


Contd. 

Section 

Blocking  

Opening  

(d) Nainpur - Balaghat (75.4 Km.)* 

Dec -2012 

Dec-2013 

* Subject to acquisition of forest land in Balaghat Distt.  

(e) NGP - Ramakona (86 Km.) 

Oct-2012 

June-2013 

(f) Ramakona - CWA (64 Km.) 

Jan -2013 

Dec – 2013 

(g) Nainpur - Seoni (76 Km.) 

Dec - 2013 

Dec-2014 

(h) Seoni - Chhindwara (64 Km.) 

Dec – 2014 

Dec - 2015


Progress of Major Items 
Jabalpur – Nainpur - Balaghat 

Sr. No 

Items 

Scope 

Progress 

1. 

Earth work

(Lakh Cum.) 

108 

40% 

2. 

Major Bridges (Nos.) 

49 

60% 

3. 

Minor Bridges (Nos.) 

313 

54%


Progress of Major Items 
Jabalpur - Sukarimangla 

Sr. No 

Items 

Scope 

Progress 

1. 

Earth work

(Lakh Cum.) 

14 

66% 

2. 

Major Bridges (Nos.) 

15 

65% 

3. 

Minor Bridges (Nos.) 

82 

68% 

Contd.


Progress of Major Items 
Nagpur - Chhindwara 

Sr. No 

Items 

Scope 

Progress 

1. 

Earth work

(Lakh Cum.) 

99.23 

20% work completed. Agency available for 27 Lakh. Cum. 

2. 

Major Bridges (Nos.) 

(a) Sub - Structure  

27 

Completed - 12

In progress – 15 

(b) Super - Structure (Nos.) 

87 steel girders 
 

W/O placed on MMR/WS and trade. 42 girders received, launching of girders taken up.  

Contd.


Sr. No 

Items 

Scope 

Progress 

3. 

Minor Bridges (Nos.) 

254 

36 - completed.

169 - Segments casted. Launching in mega block.

44 - In progress.

5 - To be closed.  

4.  

Tunnel 


Tender under finalization.  

Contd.


Targeted works 2010-11 

Name of work 

PH 

Prog. 

Remarks 

Champa – Bye Pass 

15 

20% 

Delaying  due to non-acquisition of land 

Rebuilding of Bridge NO. 99 

32 

98% 

Commissioning delaying due to non shifting of HT by CSEB 

ROB at Uslapur 

30 

82% 

Work in progress 

ROB at Raigarh – Kotarlia 

30 

50% 

Work in progress 

ROB at Raipur – Baloda Bazar  

30 

90% 

Work in progress


Name of work 

PH 

Prog. 

Remarks 

ROB at KM 867/7-8 at Durg over DRZ line. 

Deposit work 

90% 

Work in progress. 

USL – Development of Model Goods Shed. 

16 

100% 

Completed. 

RSD - Raipur development of goods shed.   

16 

100% 

Completed. 

Jharridih – Additional Dn loop. 

16 

100% 

Completed. 
 

Himgir – Additional Up loop. 

16 

87% 

Work in progress. 

Contd��


Name of work 

PH 

Prog 

Remarks 

(a) KDTR – Remodeling for dealing with addl. traffic of JSPL siding.

(b)   KDTR – Addl. Loop.  

16 

85% 

95% 

Work in progress 

Work in progress 

Bhilai – Relocation of ART/ARME train 

16 

96% 

Work in progress, GJ work being done by Div. 

BRJN – Ext.of Dn island platform for 24/26 coaches.   

16 

98% 

Completed for 24 coach length.  

Contd��


Name of work 

PH 

Prog. 

Remarks 

Durg – Development of goods shed by providing common loop. 

16 

96% 

Goods shed work completed. Signaling work to be taken up as per revision.  

BSP – Renovation of pit line NO. 1 & 2 of coaching pit line.  

42 

55% 

Work in progress 

Bhilai Peripheral Yard – Impro. in freight exam. Facility. 

42 

100% 

Completed. 

Contd��


Name of work 

PH 

Prog. 

Remarks 

Bhilai Elect. Loco Shed – Aug. of homing capacity from 150 to 175 

42 

100% 

Completed. 

BSP – Replacement of W. A. on line No. 1 & Extension of  PF No. – 4 

42 

100% 

Completed. 

BSP – Replacement of W. A. on PF No. 3 & Extension of WA on PF No. - 2 

42 

50% 

Work in progress.  

Contd��


Description  

PB/OB/LB 

Prog 

Remarks 

BSP-142 units type-II 

PB/242 

100% 

Completed.  

Raipur-96  type-II  

PB/245 

36% 

Work in progress. 48 Qtrs. by Mar-11.   

Raipur-11 type-V & 20 type-IV 

PB/248 

34% 

Work in progress. All type - V by Mar-11 
 

Raigarh- 10 type-II, 15 type-III 

LB/672 

100% 

Completed. 

PROGRESS OF QUARTERS


Description  

PB/OB/LB 

Prog 

Remarks 

BSP-Replacement of out house  50 units 

LB/270 

85% 

Work is in progress.  

BSP-Replacement of type-I 50 units 

LB/271 

85% 

Work is in progress.  

Contd.


THANK YOU


WORKS  COMPLETED IN

2009 -10 & 2010 -11 (PB) 

Sr. No. 

Name of work 

Sanc. Year 

Completed Month 

1. 

Jamga – Addl. Up loop. 

07-08 

July-09 

2. 

IB – Addl. Dn loop. 

07-08 

Sep-09 

3. 

Parmalkasa – Conversion of ��C�� class stn. into ��B�� class with 4 lines. 

05-06 

Oct-09


Sr. No. 

Name of work 

Sanc. Year 

Completed Month 

4. 

Salva - Conversion of ��C�� class stn. into ��B�� class with 4 lines. 

06-07 

Nov-09 

5. 

Belpahar – Addl. Dn loop. 

07-08 

Dec-09 

6. 

Uslapur – Development of model goods shed.  

05-06 

Apr-10 

7. 

Raipur – Store depot. Development of goods shed. 

08-09 

June-10 

8. 

Jharradih – Addl. Loop line. 

05-06 

Aug-10 

9. 

Bhilai – Jamul cement siding Electrification including yard.  

07-08 

Feb-10 

Contd.


Sr. No. 

Name of work 

Sanc. Year 

Status 

1. 

BSP : Extn. Of existing shunting neck by 180m at coaching depot.  

04-05 

Completed 
 

2. 

BEF : Development of full rake handling point.  

07-08 

Completed 

3. 

JRMG : Development of full rake handling point.  

07-08 

Completed 

STATUS OF LAW BOOK WORKS


Sr. No 

Name of work 

Sanc. Year 

Status 

4. 

MXA: Provision of dispatch signal for line No. 5, 6 & 7 towards ore yard and for line No. 2, 3 & 4 towards DUG and DRG. 

06-07 

Completed 

5. 

Surakachar : Electrification of Siding. 

06-07 

Completed 

6. 

BRJN : Electrification of Orient Collieries siding. 

06-07 

Completed 

Contd.


Sr. No. 

Name of work 

Sanc. Year 

Status 

7. 

Shifting of 04 Nos. of Cross – ovar at JRMG Railway Station.  

08-09 

Completed 

8. 

RSD : Signaling facility for reception and dispatch for line No. 7 

07-08 

Clubbed with PI work.

TDC- Mar-11  

Contd.


Name of Work 

Sanc. Year 

Anti.

Cost  

TDC 

Prg. 

Brajrajnagar – Extension of Dn island platform for 24/26 coaches.   

07-08 

2.40 

Jan-11 

98% 

Remarks

ESP & IP approved. Slewing of main line and major OHE alterations completed. PF extension work completed except stone surfacing.  

In. Crs. 

WORK IN PROGRESS


Name of Work 

Sanc. Year 

Anti. Cost 

TDC 

Prog. 

Himgir – Addl. Up loop 

07-08 

4.46 

Jan-11 

87% 

Remarks

Existing relay room will be used. 100 % E/W, bridge work and ballast supply completed. FOB - 100 % & Linking 60%. OHE - 48 foundation out of 53 done & 28 mast erected, steel received. S & T progress - 80%. CRS sanction obtained.  

Contd. 

In. Crs.


Name of Work 

Sanc. Year 

Anti. Cost 

TDC 

Prog. 

1.Kirodimalnagar – Addl. Loop.

2.Kirodimalnagar – Remodeling for dealing with additional traffic of JSPL siding. 

06-07

08-09 

4.20

6.00 

Jan-11

Jan-11 

85%

60% 

Remarks

Work is planned in two stages.

Stage -I – Up loop and one Dn loop work at KDTR.

Stage – II – 2nd Dn loop.

Connection for all 3 loops planned for simultaneous commissioning to avoid redundant works. CRS sanction awaited. E/W – 95%, Building & Bridge work – 100%, S & T – 95%, Track Linking in progress.   

Contd. 

In Crs.


Name of Work 

Sanc. Year 

Anti. Cost 

TDC 

Prog. 

Bhilai – Relocation of ART/ARME train 

08-09 

5.41 

Jan-11 

96% 

Completed work

  • Formation, track, extension of culvert.
  • Shed (40x12) 140 ton for crane.
  • S & T goomty (3mx3m) & Inspection pit.
  • Balance work in progress
  • Service building for C&W staff – Upto plinth level completed.
  • SIP & SWR to be revised after ESP alteration due to U/M LC in yard to be

    manned & relocation of point. 

  • CRS sanction for D cabin submitted on 20.09.10
 

Contd. 

In. Crs.


Name of Work 

Sanc. Year 

Anti. Cost  

TDC 

Prog. 

Durg – Development of goods shed by providing common loop & better unloading facilities.  

08-09 

7.00 
 

Jan-11 

96% 

  • Goods platform work  nearly completed.
  • Placement/withdrawal of trains being done from BSP end.
  • Connectivity from NGP end should be done along with 3rd line bet.

     Durg – Rajnandgaon to avoid repeated NI and yard modification. 

  • Renovation of existing shed for labour rest room and merchant room

     in progress.  

Contd. 

In. Crs.


Name of Work 

Sanc. Year 

Anti. Cost 

TDC 

Prog. 

Dadhapara – Belha & Urkura – Mandhar (IBS on Up & Dn lines.) 

07-08 

1.88 

Mar-11 

65% 

Full quantity of cable procured. Electrical work completed. MDH-URK commissioned on 28.7.09.Tender awarded for Dadhapara - Belha section. Work in  progress. 

Contd. 

In. Crs.


Name of Work 

Sanc. Year 

Anti. Cost 

TDC 

Prog. 

Gevra Road – Run through facility. 

08-09 

6.52 

Mar-11 

5% 

Remarks

Work proposed for dropping.  

Contd. 

In. Crs.


Name of Work 

Sanc. Year 

Anti. Cost 

TDC 

Prog. 

Mandhar – New goods terminal. 

08-09 

3.18 

NF 


Remarks

ESP Approved. Cost of work is exceeding  the abstract estimate substantially. Detailed estimate is under revision.  

Contd. 

In. Crs.


Name of Work 

Sanc. Year 

Anti.Cost 

TDC 

Prog. 

Rupond – Addl. Common loop to serve new goods shed.  

08-09 

3.46 

Apr-11 


Remarks

Scope of work revised. ESP approved. Estimate sanctioned. Civil tender finalised recently. OHE tender finalised. S & T tender opened on 05.02.10 and discharged. Fresh tender opened on 20.08.10 and under finalisation.  

Contd. 

In. Crs.


Name of Work 

Sanc. Year 

Anti. Cost 

TDC 

Prog. 

BSP Div. – IBS

(4 location) 

08-09 

6.00 

Jan-11 

20% 

Detailed estimated sanctioned. Tender awarded & work under progress. SWR��s pending in division.

                               TDC

Dadhapara - Belha  -  Oct-10

Jairamnagar - Latia  -   Nov-10

Gatora - Jairamnagr  -  Nov-10

BSP -  Gatora   -  Dec-10   

Contd. 

In. Crs.


Name of Work 

Sanc. Year 

Anti. Cost 

TDC 

Prog. 

Bhupdeopur – Remodeling for dealing with new pvt. siding. 

08-09 

10.89 

NF 


Remarks

Land acquisition required at JSG end  land plan submitted. Revised  ESP  approved.  Land acquisition proceedings stalled. Work to be truncated to avoid land acquisition and revised ESP prepared & under finalisation.  

Contd. 

In. Crs.


Name of Work 

Sanc. Year 

Anti. Cost 

TDC 

Prog. 

Bhilai – Addl. Freight maintenance depot at coal empty yard with 3 examination lines & one shunting neck of full length.  

08-09 

19.71 

Nov-11 

28% 

Contd. 

In. Crs. 

S & T and OHE tender finalised. E/W in progress. One high tension tower in the alignment is yet to be dismantled by CSEB.


Name of Work 

Sanc. Year 

Anti. Cost 

TDC 

Prog. 

Bhilai – (Exchange yard) remodeling with 2 addl. loop line by extension of D/End.   

09-10 

5.95 

Feb-12 


Remarks:-

Scope of work finalised recently by the division. Detailed estimate sanctioned during July- 10. ESP  under finalisation.  

Contd. 

In. Crs.


Name of Work 

Sanc. Year 

Anti. Cost 

TDC 

Prog. 

Himgir – Addl. Dn. Loop.   

09-10 

5.00 

NF 


Remarks:-

ESP approved. Work to be executed with 3rd line.  

Contd. 

In. Crs.


Name of Work 

Sanc. Year 

Anti. Cost 

TDC 

Prog. 

Jamga – Yard remodeling.   

09-10 

4.55 

NF 


Remarks:-

ESP approved. Work to be executed with 3rd line.  

Contd. 

In. Crs.


Name of Work 

Sanc. Year 

Anti. Cost 

TDC 

Prog. 

IB – Addl. Loop.   

09-10 

4.13 

Dec-11 


Remarks:-

Site details collected. ESP approved. Estimate vetted. Tender to be floated.    

Contd. 

In. Crs.


Name of Work 

Sanc. Year 

Anti. Cost 

TDC 

Prog. 

Mudaria – Addl. Dn. Loop. 

09-10 

3.00 

NF 


Remarks:-

Heavy cost over runs are  noticed in S & T portion of the estimate. Scope of work  reviewed and referred to Board. 

Contd. 

In. Crs.


Name of Work 

Sanc. Year 

Anti. Cost 

TDC 

Prog. 

Saragbundia – Conversion of goods shed siding into Up loop cum Dn reception line.  

09-10 

3.13 

Oct-11 


Remarks:-

ESP approved. Estimate under vetting.   

In. Crs.


JABALPUR – NAINPUR (113.5 km.) (Non – Electrified section)  

  • This part of the project is falling in Seoni, Mandla &     Jabalpur distt. of MP.
  •   Total land acquisition is 344 hec. (Pvt. 261 + Govt. 50 + Forest land 33 hec.)
  • 25 hect of Pvt./Govt. & 30 hect of forest land is balance for acquisition (Seoni district).
  • One important bridge over Narmada  (18 x  30.5 m PSC box) completed.
  •   There are three major detours (Pindarai - Ghansore 20 km, Vinayaki - Shikara 9 km, and Bargi - Kachpura 20.7 km), two minor detours in Shikara – Sukari plus mini diversions at major bridge approaches. Total length of detour alignment is 62 km. Earth Work is progressing in 56 Km length .  
 

Contd. 

Item 

Scope 

Prog.  

Remarks 

Earth work (Lakh. Cum.) 

81 

37.53 

Earth work in 6 km detour portion & in mega block is balance. 

Blanketting (Lakh cum.) 

7.7 

1.54 

About 60% qty. to be done in mega-block. 


Item 

Scope 

Prog.  

Remarks 

Major bridge (Nos.) 

33               

35% 

Tender under finalized for  32bridges.Out  of which -

Completed - 3 Br.

In Progress-21Br. 

Minor bridge (Nos.) 

194 

56 

Out of 115 bridges located in detour. 53 completed, 65 in progress. Out of 83 in same alignment pre-cast segment completed for 56   bridges & balanced 27 bridges in progress.  

Ballast (Cum.) 

244000 

14130 

18000 cum taken in Nainpur–Pendarai section. For balance tender to be invited.


Gondia – Jabalpur gauge conversion incl. Balaghat – Katangi (275.20 Km.) 

Year of sanction 

Anticipated cost. 

Exp. Upto Mar-10 

2009-10 

Overall progress 

Exp. Upto Oct.-10 

1996-97 

1038.00 

453.85 

34.48 

62% 

    Gondia – Balaghat section including MOIL siding              (42+7 Km) already commissioned.

    Balaghat–Katangi section 46.8 km completed. CRS after inspection on 23.02.2010. & section commissioned on 07.05.10


  • Track Linking – 125 Km. Indent placed for all P. way materials. 12000 Sleepers transported .
  • JBP-Gwarighat (20km) can be opened in June-2011. Thus abandoning NG alignment from JBP – Gwarighat (9.2 km).
  • TDC
 

Contd. 

Section 

Blocking  

Opening  

(a) JBP - Sukrimangla (43.41km) 

Oct-2011 

June-2012 

(b) Sukrimangla-Nainpur (70.1 km)* 

Oct-2012 

June-2013 

* Subject to acquisition of forest land in Seoni Distt.  

(c) Nainpur – Mandla Fort (42.2 Km.)  

Oct -2012 

June -2013


BALAGHAT – NAINPUR                 (75.41 km. non – electrified section) 

I- Section falling in distt. of  Balaghat & Mandla in MP state.

II-Acquisition of land

Pvt. & Govt land (50.56 hect.) – nearly 100%.

Mandla distt- 100% (20.60 hect.)

Balaghat distt(75.47 hect) case pending with MOEF since Feb-09 .


Contd. 

  • Progress of Major Items as under.
 

Item 

Scope 

Prog.  

Remarks 

Earth work (Lakh. Cum.) 

19.0 (Pre.Block) + 9.50                  ( in Block) 
 

5.65 

Balance Earth work to be done in mega block & in forest area.  

Major Bridges (Nos.) 

16 

70% 

3.5 completed.

10 under progress.

1 Bridge falling in forest area.


Item 

Scope 

Prog.  

Remarks 

Minor Bridges (Nos.) 

119 

52% 

Pre-cast Segments ready for 19 bridges. For 32 bridges tender finalised & 47  bridges on detour. 

Ballast (Cum.) 

141100 

108000 

Contract finalised for full quantity. 20% ballast being taken in depot.  

Track Linking (In Km.) 

80 Km. (Incl. Loop line) 


65% P. way material arranged.  

Contd.  

TDC - 30 months after possession of forest land i. e.  Oct - 2012. Full 75 Km will be opened in one stretch.


MANDALA FORT- NAINPUR - CHHINDWARA  
(182.25 Km. Non-Electrified) 

  • The project is being tackled in two phases i. e. (i) Mandla Fort - Nainpur (42.25 Km.) (ii) Nainpur - Chhindwara (140 Km.)
  • Final location survey of Mandla Fort – Chhindwara completed. Part detailed estimate sent to Rly. Board in May-10.
  • Tender floated for Major Bridges on 04.10.10.
  • TDC – Dec-2012
 

Year of sanction 

Anticipated cost. 

Exp. Upto Mar-10 

2009-10 

Overall progress 

Exp. Upto Oct-10 

2010-11 

556.54 



0%


NAINPUR - CHHINDWARA  
(140 Km. Non-Electrified) 

Contd.. 

  •  Final location completed 50 Km. and balance is under progress.
  • Detailed estimate will be submitted  to Rly. Board by April – 2011. 
  • TDC 
 

Section 

Blocking  

Opening  

NIR - Seoni (76 Km.) 

Dec - 13 

Dec -14 

Seoni – Chhindwara (64 Km.) 

Dec - 14 

Dec - 15


CHHINDWARA – NAGPUR GC (149.52 Km. Non-Electrified) 

  • The project is covering 53 Km. in Nagpur distt. of Maharastra & 96.52 km. in Chhindwara distt. of  M.P.
  • Total land required 328 hec. (128 hec. forest & 200 hect. private/Govt. land. 80% in M. P. & 20% in Maharastra.
  • 2nd  stage clearance of MOEF for forest land received on 30.9.09. & trees cutting in progress. 
 

Year of sanction 

Anticipated cost. 

Exp. Upto Mar-10 

2009-10 

Overall progress 

Exp. Upto Oct-10 

2005-06 

585.93 

123.23 

15.06 

23%


Item 

Scope 

Prog.  

Remarks 

Earth work (Lakh. Cum.) 

95.91 

22.08 

E/W in progress in six block sections covering 70 km. & including two major bridge approaches.   

Major Bridge (Nos.) 

27 

42% 

Sub structure of 12 bridges completed, 12 bridges in progress. Design of 3 bridges in prorgress. 43  fabricated spans received out of 87.  

Contd.


Item 

Scope 

Prog.  

Remarks 

Minor bridge (Nos.) 

254     (40  in detour) 


18 in situ bridges completed. Segmental casting completed for 139 bridges. Out of 40 bridges in detour portion work is in progress on 3 Br. Tender opened for 16 bridges under finalisation. 

Segmental 

139 

Cast in situ 

40 

Contd.  

  • Tender for 2 tunnels of 750 m & 150 m long opened on  22.03.2010.
  • Tender for 3 viaducts are invited.

    All indents for span of 12.2 m & 18.3 m placed on CEWS/Manmad. 30.5 m spans are being manufactured by agency. Indents for 45.73 m are being placed with modified 25 tonnes loading on CEWS/Manmad.

  • Ballast - Total requirement 3.36 lac. cum. Tender finalised for the stretch falling in Maharastra State of 0.84Lac cum and 0.85cum for MP.state and progressed 0.58 lac cum.
  • TDC
 

Section 

Blocking  

Opening  

CWA - ULA (25 Km. 

Dec - 10 

June -11 

ULA – Saoner (80 Km.) 

June - 11 

June -12 

Saoner - NGP (44 Km.)  

Dec -12 

June -13


Set Home | Add to Favorites

All Rights Reserved Powered by Free Document Search and Download

Copyright © 2011
This site does not host pdf,doc,ppt,xls,rtf,txt files all document are the property of their respective owners. complaint#nuokui.com
TOP